Legal Opinion

Mayor of Dawson v. Dawson Waterworks Co.

Supreme Court of Georgia

Decided August 10, 1897PublishedCited by 1 opinion

Complaint. Before Judge Sheffield. Terrell superior court. November term, 1896.

1Opinion of the CourtAtkinson, J.

This being an action against a municipal corporation for a year’s supply of water, in which the plaintiff’s right of recovery depended upon the validity of an alleged contract between it and the defendant, covering a period of years, and the evidence not affirmatively disclosing that when the contract was originally made the municipal corporation had, in the manner prescribed by the constitution of this State, made due and lawful provision for the payment of the yearly sums to become due on such contract, it was error to direct a verdict for the plaintiff.

Judgment reversed.

All the Justices…

2Cited by1 opinion

  1. City of Alma v. Indiana Air-Pump Co.Court of Appeals of Georgia · 1931