Ed Sparks & Sons v. Joe Campbell Construction Co.
Idaho Supreme Court
1Opinion of the Court
SHEPARD, Chief Justice.
This is an appeal from a judgment awarding plaintiff-respondent Ed Sparks & Sons the balance of the contract price set forth in a construction contract. The principal question presented is whether there was sufficient evidence of a mutual mistake to sustain the district court’s reformation of the contract and thereby exclude certain items otherwise required to be performed by Sparks. We reverse.
Joe Campbell Construction Company held a contract with the State of Idaho to demolish a building and construct a parking lot on the campus of Idaho State University. In turn,…
2Cases cited10 opinions
- Russ Ballard & Family Achievement Institute v. Lava Hot Springs Resort, Inc.Idaho Supreme Court · 1976
- Blankenship v. MyersIdaho Supreme Court · 1975
- In Re Estate of BogertIdaho Supreme Court · 1975
- Collins v. ParkinsonIdaho Supreme Court · 1974
- Jackson v. Blue Flame Gas CompanyIdaho Supreme Court · 1966
5 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- O'Connor v. Harger Construction, Inc.Idaho Supreme Court · 2008
- Nelson v. ArmstrongIdaho Supreme Court · 1978
- American Smelting & Refining Co. v. Idaho State Tax CommissionIdaho Supreme Court · 1979
- MATTER OF ESTATE OF COURTRIGHT v. RobertsonIdaho Supreme Court · 1978
- Cline v. Hoyle & Associates Ins., Inc.Idaho Supreme Court · 1985
8 more not listed; retrieve them via the Exa API.