This is an action to recover amounts allegedly overpaid on an oral construction contract. The jury returned a verdict for the plaintiff in the sum of $6,182.61. The plaintiff has appealed and the defendant has cross-appealed.

In 1966, Hersch Buildings, Inc., entered into an oral contract with Clarence G. Steinbrecher, a contractor, to build a packing and rendering plant for Hersch on a basic cost plus 8 percent basis. Steinbrecher finished his construction work in 1967, after total billings to Hersch of $176,586.75. Hersch paid a total of $173,434.70 to Steinbrecher and paid another $13,969.23…

2Cases cited4 opinions

  1. Kaspar v. SchackNebraska Supreme Court · 1976
  2. Umberger v. SankeyNebraska Supreme Court · 1949
  3. Illinois Central R. v. Midwestern Grain Co.District Court, W.D. Missouri · 1969
  4. Stanolind Oil & Gas Co. v. BridgesDistrict Court, E.D. Oklahoma · 1958

3Cited by13 opinions

  1. Carvalho v. Raybestos-Manhattan, Inc.Court of Appeals for the Ninth Circuit · 1986
  2. County of Douglas v. Board of Regents of University of NebraskaNebraska Supreme Court · 1982
  3. Carvalho v. Raybestos-Manhattan, Inc.Court of Appeals for the Ninth Circuit · 1986
  4. Nebraska Depository Institution Guaranty Corp. v. StastnyNebraska Supreme Court · 1993
  5. In Re Dissolution & Winding Up of KeyTronicsNebraska Supreme Court · 2008

8 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API