Leland v. Oklahoma Const. Co.
Supreme Court of Oklahoma
1Per curiam
The parties will be referred to as they appeared in the lower court, defendant in error being plaintiff and the plaintiffs in error defendants.
The plaintiff instituted this action to recover from defendant H. R. Leland $4,628.-83, the balance it claimed due for the construction of a building for said defendant, and for foreclosure of contractor’s lien on certain real estate and improvements owned by said defendant. The other parties were joined as defendants because they claimed some interest in the property which plaintiff alleged was junior to its lien. Defendant Leland answered, denying…