American Surety Co. of New York v. Wm. Cameron & Co.
Court of Appeals of Texas
1Opinion of the CourtBarcus, J.
In November, 1926, Southwell & Abbott, a partnership, made a contract with T. B. Ellison to construct a warehouse at a cost of $28,144. Under article 5 of the contract, it is provided that the final payment would be made when the work was completed and accepted by the architect, and specifically provides:
“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all pay rolls, material bills and other indebtedness connected with the work have been paid.”
Under article 9 the contractors were required to pay for all labor and material used in…
2Cases cited15 opinions
- National Bank of Cleburne v. Gulf, Colorado & Santa Fe Railway Co.Texas Supreme Court · 1902
- General Bonding & Casualty Ins. Co. v. Waples Lumber Co.Court of Appeals of Texas · 1915
- Oak Cliff Lumber Co. v. American Indemnity Co.Court of Appeals of Texas · 1924
- Lane v. UrbahnCourt of Appeals of Texas · 1924
- Reagan v. BruffCourt of Appeals of Texas · 1908
10 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- WM. Cameron & Co. v. American Surety Co. of New YorkTexas Commission of Appeals · 1932