Universal Contracting & Brick Pointing Co. v. United States
United States Court of Claims
1Opinion of the Court
ORDER
LYDON, Senior Judge:
This contract case comes before the court on motions for summary judgment filed by the parties. Defendant’s motion for summary judgment seeks dismissal of *786all four counts of the complaint, whereas plaintiff seeks summary judgment on only one count of the complaint. Plaintiff asserts that factual disputes preclude the granting of summary judgment on the other three counts of the complaint. Upon consideration of the submissions of the parties and oral argument, the court concludes that factual disputes warrant denial of the parties’ motions for summary judgment.
FACTS
On…
2Cases cited33 opinions
- United States v. Diebold, Inc.Supreme Court of the United States · 1962
- United States v. SpearinSupreme Court of the United States · 1918
- Insurance Co. v. DutcherSupreme Court of the United States · 1877
- P.J. Maffei Building Wrecking Corporation v. The United StatesCourt of Appeals for the Federal Circuit · 1984
- Columbus Railway, Power & Light Co. v. City of ColumbusSupreme Court of the United States · 1919
28 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Becho, Inc. v. United StatesUnited States Court of Federal Claims · 2000
- ThermoCor, Inc. v. United StatesUnited States Court of Federal Claims · 1996
- Conner Brothers Construction Co. v. United StatesUnited States Court of Federal Claims · 2005
- Executive Business Media, Inc. v. U.S. Department of DefenseCourt of Appeals for the Fourth Circuit · 1993
- Executive Business Media, Incorporated v. Department of DefenseCourt of Appeals for the Fourth Circuit · 1993