ADF International, Inc. v. Steelcon, Inc.
District Court, E.D. Michigan
1Opinion of the Court
OPINION AND ORDER GRANTING CROSS MOTIONS FOR SUMMARY JUDGMENT
ROBERTS, District Judge.
I. INTRODUCTION
This matter is before the Court on the parties cross-motions for summary judgment. The Court GRANTS both motions.
II. BACKGROUND
This matter arises from the construction of the Detroit Lions Stadium at Ford Field, which the parties refer to as the Detroit Lions Ford Field Project (“the Project”). The general contractor on the Project was Hunt Construction Group, Inc. (“Hunt”). Plaintiff ADF International Inc. (“ADF”) was Hunt’s structural steel subcontractor. ADF subcontracted a portion of its…
2Cases cited14 opinions
- Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
- Fed. Sec. L. Rep. P 94,768 Phil A. Street and Clyde H. Street v. J.C. Bradford & CompanyCourt of Appeals for the Sixth Circuit · 1990
- Clarence Erwin Copeland v. Mark MacHulis James StephensCourt of Appeals for the Sixth Circuit · 1995
- Ovall Dale Kendall v. The Hoover CompanyCourt of Appeals for the Sixth Circuit · 1984
- Mattie Tolton and Ronald Tolton v. American Biodyne, Inc.Court of Appeals for the Sixth Circuit · 1995
9 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Ausable River Trading Post, LLC v. Dovetail Solutions, Inc.Court of Appeals for the Sixth Circuit · 2017