Rhen v. United States
United States Court of Claims
1Opinion of the Court
MEMORANDUM OPINION
LYDON, Senior Judge:
Plaintiff, proceeding pro se, challenges the default termination of a contract he had with the Bureau of Land Management, Department of the Interior (BLM). In his complaint, plaintiff sets forth five separate claims for damages he seeks to recover emanating from this default termination. Defendant, after answer, has responded to the complaint by filing a motion for partial summary judgment as to three of the five claims, contending that, as to these three claims, there is no genuine issue as to any material fact and, accordingly, defendant is entitled to…
2Cases cited17 opinions
- Anderson v. Liberty Lobby, Inc.Supreme Court of the United States · 1986
- Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
- Sweats Fashions, Inc. v. Pannill Knitting Company, Inc.Court of Appeals for the Federal Circuit · 1987
- Pure Gold, Inc. v. Syntex (u.s.a.), Inc.Court of Appeals for the Federal Circuit · 1984
- Ramsey v. United StatesUnited States Court of Claims · 1951
12 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993
- Morrison Knudsen Corp. v. Fireman's Fund InsuranceCourt of Appeals for the Tenth Circuit · 1999
- Essen Mall Properties v. United StatesUnited States Court of Claims · 1990
- Lucas v. United StatesUnited States Court of Claims · 1992
- Denny Construction, Inc. v. City & County of Denver Ex Rel. Board of Water CommissionersSupreme Court of Colorado · 2009
3 more not listed; retrieve them via the Exa API.