Phoenix Electrical Contracting, Inc. v. Lehr Construction Corp.
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
Judgment, Supreme Court, New York County (Harold Tompkins, J.), entered April 15, 1994, after nonjury trial, in favor of plaintiff subcontractor and against defendant-appellant general contractor in the principal amount of $186,467.64, plus interest from November 3,1987, unanimously modified, on the law and the facts, to reduce the principal amount to $58,888.78, with interest from November 3, 1988, and otherwise affirmed, without costs.
Defendant Lehr, the general contractor on a renovation contract for premises occupied by defendant Rose Associates, should not have been held liable for delay…
2Cases cited5 opinions
- Ford v. Unity HospitalNew York Court of Appeals · 1973
- National Contracting Co. v. Hudson River Water Power Co.New York Court of Appeals · 1908
- AEB & Associates Design Group, Inc. v. Tonka Corp.District Court, S.D. New York · 1994
- Triangle Sheet Metal Works, Inc. v. JAMES H. MERRITT & CO.New York Court of Appeals · 1991
- Gonfiantini v. ZinoAppellate Division of the Supreme Court of the State of New York · 1992
3Cited by5 opinions
- Sequa Corp. v. GBJ Corp.Court of Appeals for the Second Circuit · 1998
- Barry, Bette & Led Duke, Inc. v. StateAppellate Division of the Supreme Court of the State of New York · 1998
- Douglas Construction, Inc. v. MarcaisAppellate Division of the Supreme Court of the State of New York · 1997
- Brian Trematore Plumbing & Heating, Inc. v. Walsh Construction Group, LLCDistrict Court, S.D. New York · 2021
- Sequa Corporation and Sequa Capital Corporation, Plaintiffs-Appellants-Cross-Appellees v. Gbj Corporation, Jeffrey J. Gelmin, and Topaz Capital Corporation, Defendants-Appellees-Cross-Appellants. Gbj Corporation, Jeffrey J. Gelmin, and Topaz Capital Corporation v. Butler, Fitzgerald & Potter, a Professional CorporationCourt of Appeals for the Second Circuit · 1998