James Hamilton Construction Co. v. State ex rel. New Mexico State Highway & Transportation Department
New Mexico Court of Appeals
1Opinion of the Court
OPINION
SUTIN, Judge.
{1} James Hamilton Construction Company (Hamilton) protested a construction bid award on the ground the bid was not signed. The New Mexico State Highway and Transportation Department (the Department) denied the protest on the ground the protest was untimely. The district court agreed. The Department also determined on the merits of the protest that the lack of a signature on the winning bid was not fatal. The district court did not make a ruling on this issue. We agree that the protest was not timely and affirm. We need not and therefore do not address the signature issue.
B…
2Cases cited5 opinions
- Rio Grande Chapter of the Sierra Club v. New Mexico Mining CommissionNew Mexico Supreme Court · 2002
- Johnson v. New Mexico Oil Conservation CommissionNew Mexico Supreme Court · 1999
- Taylor v. Hanchett Oil Co.New Mexico Supreme Court · 1933
- C.F.T. Development, LLC v. Board of County CommissionersNew Mexico Court of Appeals · 2001
- Ambassador East Apts., Investors v. Ambassador East InvestmentNew Mexico Court of Appeals · 1987