Nixon v. Hansford
District of Columbia Court of Appeals
1Opinion of the Court
BELSON, Associate Judge:
Appellant Rosa Lee Nixon appeals from a judgment awarding appellee Norman Hansford $1,200.00 as the amount due under a home improvement contract and dismissing Nixon’s counterclaim for recovery of a $1,150.00 deposit on the contract. Nixon contends that the trial court erred in its ruling because Hansford, an unlicensed home improvement contractor, accepted partial payment in advance of the completion of the contract in violation of the provisions of the home improvement regulations, 16 DCMR § 800.1 (1987). We agree.
The facts in this case, as found by the trial court…
2Cases cited7 opinions
- Truitt v. MillerDistrict of Columbia Court of Appeals · 1979
- Miller v. Peoples Contractors, Ltd.District of Columbia Court of Appeals · 1969
- Bathroom Design Institute v. ParkerDistrict of Columbia Court of Appeals · 1974
- Billes v. BaileyDistrict of Columbia Court of Appeals · 1989
- Erwin v. CraftDistrict of Columbia Court of Appeals · 1982
2 more not listed; retrieve them via the Exa API.
3Cited by16 opinions
- Beard v. Goodyear Tire & Rubber Co.District of Columbia Court of Appeals · 1991
- Cevern, Inc. v. FerbishDistrict of Columbia Court of Appeals · 1995
- Capital Construction Co. v. Plaza West Cooperative Ass'nDistrict of Columbia Court of Appeals · 1992
- Remsen Partners, Ltd. v. Stephen A. Goldberg Co.District of Columbia Court of Appeals · 2000
- Djourabchi v. SelfDistrict Court, District of Columbia · 2008
11 more not listed; retrieve them via the Exa API.