Ideal Concrete Block Co. v. Fries
Massachusetts District Court, Appellate Division
1Opinion of the CourtParker, J.
This is an action of contract to recover $180.00 plus interest of $19.00 for rental by the defendant of certain heating equipment.
The third paragraph of the Defendant’s Answer is as follows:
“3. And further answering the Defendant denies the plaintiff is a corporation”.
Before final argument, the defendant made the following request for ruling:
“The finding of the Court must be for the defendant because the plaintiff has failed to prove that it is a corporation”.
The court denied this request and the defendant claimed a report on its denial.
The report shows that no proof of the plaintiff’s…
2Cases cited6 opinions
- Salvato v. DiSILVA TRANSPORTATION CO. INC.Massachusetts Supreme Judicial Court · 1952
- Scholl v. GilmanMassachusetts Supreme Judicial Court · 1928
- McDuffee v. KelseyMassachusetts Supreme Judicial Court · 1942
- Spooner v. GilmoreMassachusetts Supreme Judicial Court · 1884
- Cabana v. ConclaveMassachusetts Supreme Judicial Court · 1893
1 more not listed; retrieve them via the Exa API.