H. R. Johnson Construction Co. v. Board of Education
Lake County Court of Common Pleas
1Opinion of the CourtSimmoNS, J.
This case comes before the court for decision on defendants’ motion to dismiss the petition, the pleadings, stipulation of facts and other evidence at trial.
After considering these, written briefs and the law, I rule as follows:(1) Plaintiff has standing to challenge the contract award to Lunka and its petition states a cause of action. The motion is overruled.(2) The contract between the board and Lunka is illegal and void. Defendants are permanently enjoined against further performing it.(3) Plaintiff’s prayer that the board be ordered to award a contract to it for construction of the…
2Cases cited3 opinions
- Wayman v. Board of EducationOhio Supreme Court · 1966
- Saunders v. Board of EducationOhio Court of Appeals · 1944
- Rice v. CampbellOhio Court of Appeals · 1942
3Cited by3 opinions
- Power Sytems Analysis, Inc. v. City of BloomerCourt of Appeals of Wisconsin · 1995
- PHC, Inc. v. Village of Kelleys IslandOhio Court of Appeals · 1991
- Power Sytems Analysis, Inc. v. City of BloomerCourt of Appeals of Wisconsin · 1995