Decided January 24, 1975No. 447-73PublishedCited by 1 opinion

1Opinion of the Court

Contracts; disputes; exhaustion of administratwe remedies; delay of contracting officer in rendering decision. — On January 24,1975 the court issued the following order:

Before davis, Judge, Presiding, kashiwa and kunzig, Judges.

“This case comes before the court on defendant’s motion, filed March 22,1974, for summary judgment and on plaintiff’s motion, filed April 29,1974, for summary judgment, having been submitted and considered on the briefs and oral argument of counsel.

“Defendant seeks dismissal of the petition on the ground that plaintiff failed to exhaust its administrative remedies in…

2Cases cited5 opinions

  1. Zidell Explorations, Inc. v. The United StatesUnited States Court of Claims · 1970
  2. Clement Brothers Company, Inc. v. The United StatesUnited States Court of Claims · 1970
  3. Marwil Products Co., a Corporation v. The United StatesUnited States Court of Claims · 1969
  4. Sun Shipbuilding & Dry Dock Co. v. United StatesUnited States Court of Claims · 1972
  5. WarrenUnited States Court of Claims · 1974

3Cited by1 opinion

  1. SCM Corp.United States Court of Claims · 1976

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API