E. I. DuPont de Nemours Powder Co. v. Louisville & Nashville Railroad
Court of Appeals of Kentucky
Appeal from Laurel Circuit Court.
1Opinion of the Court
*594Opinion op the Court by
Chief Justice Hobson
Reversing.
The Louisville & Nashville Railroad Company made a contract with the Edington-Griffitts Construction Company for the construction of a part of its line of railway. That company sub-contracted a part of the work to the Ryan-Battin Construction Company, who, in turn, subcontracted a part of the work to the W. F. Garretson Company, who bought of the E. I. duPont de Nemours Powder Company a lot of material and supplies for the work amounting to $2,988.30. The powder company not having been paid for the material furnished for the work, duly…