Supreme Court of Vermont

Decided August 25, 2017No. 16–125PublishedCited by 3 opinions

1Opinion of the CourtReiber, C.J.

¶ 1. The Town of New Haven appeals the Public Service Board's issuance of a certificate of public good (CPG) to New Haven GLC Solar, LLC (GLC) to construct a net-metered solar array within the Town. The Town asserts that the Board acted arbitrarily and in excess of its lawful authority by issuing the CPG without holding a hearing on significant issues raised by the Town, without giving due consideration to the Town's recommendations or the town plan, and without following its own mandatory regulations regarding interconnection procedures. We reverse the Board's issuance of the CPG and remand…

2Cases cited6 opinions

  1. In Re Amended Petition of UPC Vermont Wind, LLCSupreme Court of Vermont · 2009
  2. In Re Entergy Nuclear Vermont Yankee, LLCSupreme Court of Vermont · 2007
  3. In Re Green Mountain Power Corp.Supreme Court of Vermont · 1994
  4. Gasoline Marketers of Vermont, Inc. v. Agency of Natural ResourcesSupreme Court of Vermont · 1999
  5. In re Petition of Rutland Renewable Energy, LLC for Certificate of Public Good Pursuant to 30 V.S.A. § 248Supreme Court of Vermont · 2016

1 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. In re Petition of Stowe Cady Hill Solar, LLCSupreme Court of Vermont · 2018
  2. In re Petition of LK Holdings, LLCSupreme Court of Vermont · 2018
  3. In re Application of Derby GLC Solar, LLCSupreme Court of Vermont · 2019

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API