Thompson-McDonald Lumber Co. v. Morawetz
Supreme Court of Minnesota
Action in tbe district court for Dakota county to recover judgment for $297.95 and to foreclose a mechanic’s lien for tbe same upon tbe premises described in tbe complaint. Tbe case was tried before Johnson, J., who made findings and ordered judgment in favor of plaintiff. Erom tbe judgment entered pursuant to tbe order for judgment, defendant Morawetz appealed.
1Opinion of the Court
Brown, 0. J.
Defendant Morawetz entered into a contract with defendant Offrell for tbe construction of a building upon premises owned by *278•him, Offrell agreeing to furnish all labor and material. On February 27, 1912, Offrell, the contractor, purchased from plaintiff certain material to be used in the construction of the building, of the value of $288.24, and the same was used for that purpose. On March 30, 1912, the contractor purchased other and additional material for the same use and purpose of the value of $9.71. The material so furnished was not paid for, and within 90 days from the date…
2Cases cited7 opinions
- Johnson v. StarrettSupreme Court of Minnesota · 1914
- Wentworth v. TubbsSupreme Court of Minnesota · 1893
- Burns v. SewellSupreme Court of Minnesota · 1892
- Berger v. TurnbladSupreme Court of Minnesota · 1906
- John Paul Lumber Co. v. HormelSupreme Court of Minnesota · 1895
2 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Lamoreaux v. AnderschSupreme Court of Minnesota · 1915
- In the Matter of Wiltse Brothers Corporation, Bankrupt. Whitehead & Kales Company v. William H. Dempster, TrusteeCourt of Appeals for the Sixth Circuit · 1966
- Tabet v. DavenportNew Mexico Supreme Court · 1953
- Northland Pine Co. v. Northern Insulating Co.Supreme Court of Minnesota · 1920
- Minneapolis Sash & Door Co. v. HeddenSupreme Court of Minnesota · 1915
8 more not listed; retrieve them via the Exa API.