Westinghouse Electric Corp. v. Mill & Elevator Co.
Supreme Court of Iowa
1Opinion of the Court
Garfield, 0. J.
— The question presented is the liability of defendant surety on a construction bond to plaintiff-subcontractor from which defendant principal contractor purchased material in performing the contract. The answer depends on the proper construction of the contractor’s bond and the contract made part thereof. Following trial in equity, mainly on stipulated facts, judgment was entered for plaintiff against defendants’ contractor and its surety. These defendants and the owner appeal.
Plaintiff-subcontractor is Westinghouse Electric Corporation. Defendant principal contractor is Mill…
2Cases cited11 opinions
- Jordan v. KavanaughSupreme Court of Iowa · 1884
- Baker & Co. v. BryanSupreme Court of Iowa · 1884
- Hipwell v. the National Surety Co.Supreme Court of Iowa · 1905
- Chicago & Northwestern Railway Co. v. KrammeSupreme Court of Iowa · 1953
- Bourrett v. W. M. Bride Construction Co.Supreme Court of Iowa · 1957
6 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Cretex Companies, Inc. v. Construction Leaders, Inc.Supreme Court of Minnesota · 1984
- Ore-Ida Potato Products, Inc. v. United Pacific InsuranceIdaho Supreme Court · 1964
- National Bank v. Equity InvestorsWashington Supreme Court · 1976
- Amelco Window Corp. v. Fed. Ins. Co.New Jersey Superior Court Appellate Division · 1974
- Royal Indemnity Co. v. Alexander Industries, Inc. Ex Rel. Berger Acoustical Co.Supreme Court of Delaware · 1965