United States ex rel. Ackerman v. Holloway Co.
District Court, D. New Mexico
1Opinion of the Court
ROGERS, District Judge.
For the purpose of this phase of each of the above causes, they were consolidated for a hearing on the matter of whether the complaints in said causes were prematurely filed. The question of prematurity of filing was raised by the second defense of the answer filed in each cause, which, in effect, stated that the contract between each of the plaintiffs, who were sub-contractors to the principal contractor, Holloway Company, provided, in part, as follows:
“No payment is due hereunder, whether a progress payment or final payment, until such progress payment or final…
2Cases cited3 opinions
- Grandview Inland Fruit Co. v. Hartford Fire InsuranceWashington Supreme Court · 1937
- Bowersock v. SmithSupreme Court of the United States · 1917
- United States ex rel. Bailey v. United Pacific Ins.District Court, D. New Mexico · 1954
3Cited by6 opinions
- United States ex rel. Tusco, Inc. v. Clark Construction Group, LLCDistrict Court, D. Maryland · 2016
- Travis Equipment Co. v. D & L Construction Co. & AssociatesDistrict Court, W.D. Missouri · 1963
- United States ex rel. Kitchens to Go v. John C. Grimberg Co.District Court, E.D. Virginia · 2017
- Jefferson Construction Co. v. United States of America, for the Use and Benefit of Roy Bacon, Mel Trucking & Contracting Co., Inc. v. United States of America, for the Use and Benefit of Roy BaconCourt of Appeals for the First Circuit · 1960
- Jefferson Construction Co. v. United StatesCourt of Appeals for the First Circuit · 1960
1 more not listed; retrieve them via the Exa API.