Legal Opinion

Oakley v. Duluth Superior Dredging Co.

Michigan Supreme Court

Decided June 21, 1923No. Docket No. 91PublishedCited by 3 opinions

1Opinion of the CourtClakk, J.

In the spring of 1919 defendant had a contract with the owner to construct a dike about certain land at Windmill Point, Wayne county, and to fill the enclosure with soil pumped by sand suckers from the bottom of the lake. It sublet the constructing of a certain dike and the leveling thereof after filling was done to plaintiff at a price of 50 cents per linear foot. When he had constructed 488 feet it was found that the dike was of insufficient height. He obtained a larger trenching machine to construct a higher dike for which he was to be paid 70 cents per linear foot, including both…

2Cases cited14 opinions

  1. Hosmer v. WilsonMichigan Supreme Court · 1859
  2. Allen v. McKibbinMichigan Supreme Court · 1858
  3. Whipple v. ParkerMichigan Supreme Court · 1874
  4. Wildey v. Fractional School District Number OneMichigan Supreme Court · 1872
  5. Fuller v. RiceMichigan Supreme Court · 1884

9 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Antonoff v. BassoMichigan Supreme Court · 1956
  2. Goldblum v. United Automobile, Aircraft & Agricultural Implement Workers Ford Local No. 50Michigan Supreme Court · 1947
  3. Adams v. HealyMichigan Supreme Court · 1924