In September, 1926, the plaintiff and defendant entered into a contract in which the former agreed to excavate to the proper level and construct a concrete sidewalk and curb in front of the latter’s property for the agreed price of $420, being at the rate of $3 per running foot for one hundred and forty feet. The plaintiff agreed to start the work within a week and to complete it before cold weather set in. The plaintiff did not start work until December 4th, 1926. He removed a strip of earth along the frontage of defendant’s premises to a width of twelve feet and a depth of eight feet and…
2Cases cited7 opinions
- M. J. Daly & Sons, Inc. v. New Haven Hotel Co.Supreme Court of Connecticut · 1917
- Elliott v. CaldwellSupreme Court of Minnesota · 1890
- Pinches v. Swedish Evangelical Lutheran ChurchSupreme Court of Connecticut · 1887
- Pollak v. Danbury Manufacturing Co.Supreme Court of Connecticut · 1925
- Fagerholm v. NielsonSupreme Court of Connecticut · 1919
2 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Anderson v. YaworskiSupreme Court of Connecticut · 1935
- David M. Somers & Associates, P.C. v. BuschSupreme Court of Connecticut · 2007
- Automobile Insurance v. Model Family Laundries, Inc.Supreme Court of Connecticut · 1947
- Loomis v. Fifth School DistrictSupreme Court of Connecticut · 1929
- Vincenzi v. CerroSupreme Court of Connecticut · 1982
8 more not listed; retrieve them via the Exa API.