AAC CORPORATION v. Reed
Washington Supreme Court
1Opinion of the CourtWeaver, J.
-This is an action to foreclose a lien for labor and material timely filed against the real property involved.
Upon motion of defendants, Richard J. Rush and wife, the trial court entered summary judgment holding that the land in question “is free and clear of that certain lien claimed by the plaintiff.” The judgment is based upon the court’s conclusion that plaintiff’s action had not been commenced within the time fixed by statute.
The facts are not in dispute. In 1962, Aluminum Construction, Inc., furnished labor and material for a building on the land involved at the request of Charles H.…
2Cases cited7 opinions
- Weinberg v. NaherWashington Supreme Court · 1909
- Puget Sound Mutual Savings Bank v. LillionsWashington Supreme Court · 1957
- Gunby v. IngramWashington Supreme Court · 1910
- Coman v. PetersWashington Supreme Court · 1909
- De Gooyer v. Northwest Trust & State BankWashington Supreme Court · 1924
2 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- Ross v. ScannellWashington Supreme Court · 1982
- 4518 S. 256th, LLC v. Karen L. Gibbon, PSCourt of Appeals of Washington · 2016
- Kevin E. Edmundson, Res. v. Carrington Mortgage Services, Llc, App.Court of Appeals of Washington · 2016
- Glassmaker v. RicardCourt of Appeals of Washington · 1979
- Sandra M. Merceri v. The Bank Of New York MellonCourt of Appeals of Washington · 2018
14 more not listed; retrieve them via the Exa API.