Pine Hill Estates Inc. v. Stone
Massachusetts District Court, Appellate Division
1Opinion of the CourtBlack, P.J.
Counsel for the defendant in this case has filed a “Motion to Extend Time For Approval of a Draft Report” which contains two requests; *100namely (1) that the time be extended for allowance of a Draft Report upon ' which the trial judge has failed to act; and, (2) that this court establish a report as provided under Mass. R. Civ. P., Rule 64(c) (5).
A review of the docket sheet disclosed that this case involves a Summary ■ Process action, as to which there was a finding for the plaintiff after a hearing in the Taunton Division. Thereafter, the defendant filed a Notice of Appeal-Request for Draft…
2Cases cited2 opinions
- Shea v. Neponset River Marine & Sportfishing, Inc.Massachusetts Appeals Court · 1982
- Hunters Brook Realty Trust v. SampsonMassachusetts District Court, Appellate Division · 1980
3Cited by3 opinions
- Emerson v. DuboisMassachusetts District Court, Appellate Division · 1989
- Corcoran Management Co. v. MichaelangeloMassachusetts District Court, Appellate Division · 1996
- Gloucester Bank & Trust Co. v. FerraraMassachusetts District Court, Appellate Division · 1998