Appeal from an order of the Supreme Court, Onondaga County (John V Centra, J.), entered August 20, 2002. The order, inter alia, denied plaintiffs motion for partial summary judgment on the issue of liability under Labor Law § 240 (1).
It is hereby ordered that the order so appealed from be and the same hereby is unanimously affirmed without costs.
Memorandum: Plaintiff commenced this action seeking damages for injuries that he sustained in an accident at a construction site, asserting, inter alia, claims under Labor Law § 240 (1) and § 241 (6). The record establishes that plaintiff was injured…
2Cases cited14 opinions
- Ross v. Curtis-Palmer Hydro-Electric Co.New York Court of Appeals · 1993
- Russin v. Louis N. Picciano & SonNew York Court of Appeals · 1981
- Narducci v. Manhasset Bay AssociatesNew York Court of Appeals · 2001
- Misseritti v. Mark IV Construction Co.New York Court of Appeals · 1995
- Rodriguez v. Margaret Tietz Center for Nursing Care, Inc.New York Court of Appeals · 1994
9 more not listed; retrieve them via the Exa API.
3Cited by4 opinions
- Uzar v. Louis P. Ciminelli Construction Co.Appellate Division of the Supreme Court of the State of New York · 2008
- Predmore v. EJ Construction Group, Inc.Appellate Division of the Supreme Court of the State of New York · 2008
- Millard v. Hueber-Breuer Construction Co.Appellate Division of the Supreme Court of the State of New York · 2004
- Wiley v. Marjam Supply Co., Inc.Appellate Division of the Supreme Court of the State of New York · 2018