Legal Opinion

Lester v. United States

United States Court of Claims

Decided October 15, 1863PublishedCited by 1 opinion

On the Proofs,

1Opinion of the CourtCasey, C. J.

On the 9 th of February, 1855, Colonel William Turnbull, who was in charge of the improvement of the harbors in the northern lakes, concluded a contract with the claimants for the delivery of the following materials at the harbor of Dunkirk, New York, viz :

“ 1, 054 pieces hemlock timber, 30 feet long........ 12x12

918 pieces do do 20 do 12x12

204 pieces pine do 30 do 12x12

204 pieces do do 20 do 12x12

51 pieces oak do 30 do 12x12

51 pieces do do 30 do 12x12

68 pieces do do 30 do 12x6

5 pieces do do 10 do 16x16

*5324, 650 feet, board measure, 3-inch pine plank, 10 feet long.

4, 792 white oak treenails, 2…

2Cases cited2 opinions

  1. Tayloe v. T. & S. SandifordSupreme Court of the United States · 1822
  2. Jackson ex dem. Norton v. SheldonNew York Supreme Court · 1826

3Cited by1 opinion

  1. New Jersey Foundry & Machine Co. v. United StatesUnited States Court of Claims · 1909

Showing a preview — retrieve the full document via the Exa API.