MEMORANDUM OPINION DENYING DEBTORS’ MOTION FOR STAY PENDING APPEAL

JACK B. SCHMETTERER, Bankruptcy Judge.

INTRODUCTION

Defendant William A. Pope Company (“Pope”) and Plaintiff-Debtor Raymond Management Services, Inc., n/k/a Raymond Professional Group-Design/Build, Inc., (“RMS”) contracted to construct a project for the owner of a power facility. 1 Plaintiff-Debtor Raymond Professional Group, Inc., (“RPG”) was not part of that contract. Pope and RMS set up an account (the “Account”) on which they had joint signatory powers subject to contractual claims against each other to be resolved after…

2Cases cited16 opinions

  1. Allen v. McCurrySupreme Court of the United States · 1980
  2. Northern Indiana Public Service Company, an Indiana Corporation v. Carbon County Coal Company, a PartnershipCourt of Appeals for the Seventh Circuit · 1986
  3. In Re Auto-Train Corporation, Inc.Court of Appeals for the D.C. Circuit · 1987
  4. In the Matter of Forty-Eight Insulations, Incorporated, Debtor. Appeal of Maritime Asbestos 1Court of Appeals for the Seventh Circuit · 1997
  5. In Re Snider Bros., Inc.United States Bankruptcy Court, D. Massachusetts · 1982

11 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. In re QuadeUnited States Bankruptcy Court, N.D. Illinois · 2013
  2. Gysum Resources Materials LLC v. Rep-Clark LLCDistrict Court, D. Nevada · 2023

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API