Loehler v. United States
United States Court of Claims
1Opinion of the CourtWilliams, Judge
Plaintiff brings suit to recover damages because. of the alleged breach of a contract entered into between plaintiff and the United States whereby plaintiff. agreed to furnish all labor and materials, and perform all work required for the construction of a bath house, swimming pool, beginners’ pool, pump and filter room, pergola and shelter, and two sand boxes, together with plumbing and electrical work, brick and concrete paving, mechanical equipment and piping for filling, emptying, and cleaning the pools, and for recirculating and purifying the water in the pools, on McKinley High School…
2Cases cited4 opinions
- Rowzee v. PierceMississippi Supreme Court · 1898
- McCullough v. Board of EducationCalifornia Supreme Court · 1876
- Kelly v. Town of HaywardCalifornia Supreme Court · 1923
- Board of Education v. City of Kansas CitySupreme Court of Kansas · 1901