Willoughby Roofing and Supply Company, Inc. v. Kajima International, Inc.
Court of Appeals for the Eleventh Circuit
1Per curiam
We affirm the judgment in this case substantially on the basis of the district court’s opinion reported at 598 F.Supp. 353 (N.D. Ala.1984). We write here merely to address one contention not considered by the court’s opinion below.
In addition to the arbitration clause cited by the district court, see 598 F.Supp. at 355, the contract in question also contained the following provision:
Section 6.06. Termination. KII shall have the right at any time by written notice to the Subcontractor to terminate the Subcontract and require the Subcontractor to cease work thereunder; in which case, provided…
2Cases cited5 opinions
- Moses H. Cone Memorial Hospital v. Mercury Construction Corp.Supreme Court of the United States · 1983
- United Steelworkers v. Enterprise Wheel & Car Corp.Supreme Court of the United States · 1960
- Geohagan v. General Motors Corp.Supreme Court of Alabama · 1973
- Willoughby Roofing & Supply Co. v. Kajima International, Inc.District Court, N.D. Alabama · 1984
- John Deere Indus. Equipment Co. v. KellerSupreme Court of Alabama · 1983
3Cited by45 opinions
- Parker v. Connors Steel Co.Court of Appeals for the Eleventh Circuit · 1988
- James W. Bonar and Beverly J. Bonar v. Dean Witter Reynolds, Inc., John S. Mc Nally, Jr., Ed LeavenworthCourt of Appeals for the Eleventh Circuit · 1988
- Ahmad Baravati v. Josephthal, Lyon & Ross, Incorporated, and Peter SheibCourt of Appeals for the Seventh Circuit · 1994
- Bowen v. Amoco Pipeline Co.Court of Appeals for the Tenth Circuit · 2001
- Raytheon Company v. Automated Business Systems, Inc.Court of Appeals for the First Circuit · 1989
40 more not listed; retrieve them via the Exa API.