Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
Massachusetts Supreme Judicial Court
1Opinion of the CourtGants, C.J.
This case requires us to resolve three issues regarding a public construction contract that implements the construction management at risk delivery method, pursuant to G. L. c. 149A: (1) Does the owner who furnishes the plans and specifications in a public construction management at risk project give an implied warranty of their sufficiency for the purpose intended, as the owner does under our common law in traditional design-bid-build construction projects? (2) If so, did the parties to the construction management at risk contract in this case disclaim the implied warranty? (3) If they did…
2Cases cited18 opinions
- United States v. SpearinSupreme Court of the United States · 1918
- Iannacchino v. Ford Motor Co.Massachusetts Supreme Judicial Court · 2008
- Marram v. Kobrick Offshore Fund, Ltd.Massachusetts Supreme Judicial Court · 2004
- Galiastro v. Mortgage Electronic Registration Systems, Inc.Massachusetts Supreme Judicial Court · 2014
- Flagg v. AliMed, Inc.Massachusetts Supreme Judicial Court · 2013
13 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- Edwards v. CommonwealthMassachusetts Supreme Judicial Court · 2017
- Burbank Apartments Tenant Association v. KargmanMassachusetts Supreme Judicial Court · 2016
- Goodwin v. Lee Public SchoolsMassachusetts Supreme Judicial Court · 2016
- Arsenault v. BhattacharyaMassachusetts Appeals Court · 2016
- CITY OF BOSTON v. QUINCY CONSERVATION COMMISSION & OthersMassachusetts Superior Court · 2020
5 more not listed; retrieve them via the Exa API.