General Electric Supply Co. v. Mt. Wheeler Power, Inc.
Nevada Supreme Court
1Opinion of the Court
OPINION
2Per curiam
Respondent sought damages resulting from appellant’s breach of contract. At the conclusion of a trial without jury, the district court concluded appellant had breached its contract t- supply material to respondent and awarded respondent costs, plus damages in the amount of $164,460.30. Appellant’s only cognizable contentions are (1) the evidence adduced at trial fails to support the district court’s findings; and, (2) the district court erred in awarding damages. We disagree.
1. Appellant contends the district court erred in finding (a) it had breached the contract by failing to make…
3Cases cited3 opinions
- Fireman's Fund Insurance Company v. ShawcrossNevada Supreme Court · 1968
- Eaton v. J. H. Inc.Nevada Supreme Court · 1978
- Havas v. EngebregsonNevada Supreme Court · 1978
4Cited by11 opinions
- Rancho Pescado, Inc. v. Northwestern Mutual Life InsuranceCourt of Appeals of Arizona · 1984
- Guard v. P & R ENTERPRISES, INC.Alaska Supreme Court · 1981
- American Heritage, Inc. v. Nevada Gold & Casino, Inc., Texas Court of Appeals, 1st District (Houston)2008
- DANIEL, MANN, JOHNSON, ETC. v. Hilton HotelsNevada Supreme Court · 1982
- Sierra Creek Ranch, Inc. v. J. I. CaseNevada Supreme Court · 1981
6 more not listed; retrieve them via the Exa API.