Hetherington Letter Co. v. O. F. Paulson Construction Co.
Supreme Court of Iowa
1Per curiam
This is a sequel to our opinion in Hetherington Letter Co. v. O. F. Paulson Const. Co., Iowa, 171 N.W.2d 264 as supplemented in 173 N.W.2d 575. We there found against Hetherington on the appeal and on Paulson’s cross-appeal found it entitled to recover an additional amount. The trial court had entered a $13,901.09 judgment against Hetherington with five percent interest per annum from August 16, 1960.
At page 269, 171 N.W.2d, we stated: “This court now holds defendant is entitled to have its mechanic’s lien established to secure payment of $5,331.60 balance due on the contract, plus $14,572.82…
2Cases cited4 opinions
- Arnold v. ArnoldSupreme Court of Iowa · 1966
- Iowa-Illinois Gas and Electric Company v. GaffneySupreme Court of Iowa · 1964
- Hetherington Letter Co. v. O. F. Paulson Construction Co.Supreme Court of Iowa · 1969
- Hetherington Letter Co. v. O. F. Paulson Construction Co.Supreme Court of Iowa · 1970
3Cited by2 opinions
- State v. HallSupreme Court of Iowa · 1977
- Muchmore Equipment, Inc. v. GroverSupreme Court of Iowa · 1983