Legal Opinion

Ruegsegger v. BANGOR TOWNSHIP RELIEF DRAIN

Michigan Court of Appeals

Decided July 7, 1983No. Docket 61176PublishedCited by 4 opinions

1Per curiam

The dispute herein arose out of a release of a right-of-way to appellants obtained from appellee Ruegsegger to enable appellants to proceed with a construction project involving the installation of a storm sewer and drain. Mr. Bacon, an employee of appellants’ engineering firm, Edmands Engineering, Inc., negotiated the agreement on behalf of appellants. After concluding the preliminary negotiations with appellee Ruegsegger and obtaining approval from appellants’ board, Mr. Bacon took the release to appellee Ruegsegger for completion. Prior to completion a footnote which is the primary subject…

2Cases cited3 opinions

  1. Miller v. Magline, Inc.Michigan Court of Appeals · 1977
  2. Schneider v. FoxMichigan Court of Appeals · 1977
  3. Shelby Township v. BloomstrandMichigan Court of Appeals · 1975

3Cited by4 opinions

  1. Bregman v. MeehanNew York Supreme Court · 1984
  2. Edidin v. Detroit Economic Growth Corp.Michigan Court of Appeals · 1984
  3. Luxury Limousine, Inc. v. National Indemnity CompanyDistrict Court, E.D. Michigan · 2019
  4. M. Jacob & Sons v. Pure Steeps Beverage, LLCDistrict Court, E.D. Michigan · 2021

Showing a preview — retrieve the full document via the Exa API.