Varner Construction Co. v. Mid-South Specialties, Inc.
Tennessee Supreme Court
1Opinion of the Court
OPINION
BROCK, Justice.
This is an action to recover upon a contractor’s bond conditioned to pay for labor and materials furnished in the performance of a contract to construct a fire station for the City of Memphis. We must determine which statute of limitations is applicable and whether or not the suit is barred.
Defendant, Varner Construction Company, was the general contractor and executed the bond in question as required by T.C.A. § 12-417. The plaintiff, Mid-South Specialties, a remote subcontractor, furnished labor and materials to Southwest Roofing and Supply, Inc., a subcontractor, for…
2Cases cited2 opinions
- Hogan v. Walsh & Wells, Inc.Tennessee Supreme Court · 1944
- City of Knoxville v. Melvin F. Burgess, Inc.Tennessee Supreme Court · 1943
3Cited by3 opinions
- Aetna Casualty & Surety Co. v. WoodsTennessee Supreme Court · 1978
- Wal-Board Supply Co., Inc. v. DanielsCourt of Appeals of Tennessee · 1981
- Malcolm Mills v. Ken Hancock, Ind.Court of Appeals of Tennessee · 1998