Legal Opinion

City of Knoxville v. Melvin F. Burgess, Inc.

Tennessee Supreme Court

Decided November 20, 1943PublishedCited by 9 opinions

1Opinion of the Court

Me. Chief Justice .Gkeen

delivered the opinion of the Court.

City of Knoxville, through a subsidiary, entered into a contract with Melvin F. Burgess, Inc., to construct an extension to the City’s electric distribution system at a cost of $200,000'. The work was completed and accepted and there remains in the hands of the City a balance of some $19,000 retained percentage.

It appears from a bill tiled by the City that a number of persons furnishing material for this work have not been paid by the contractor. It further appears that the contractor executed a bond with New Amsterdam Casualty…

2Cases cited8 opinions

  1. Equitable Surety Co. v. United States Ex Rel. McMillanSupreme Court of the United States · 1914
  2. Cass v. SmithTennessee Supreme Court · 1921
  3. Frix v. StateTennessee Supreme Court · 1923
  4. City of Bristol v. BostwickTennessee Supreme Court · 1917
  5. United States Fidelity & Guaranty Co. v. Tafel Electric Co.Court of Appeals of Kentucky (pre-1976) · 1935

3 more not listed; retrieve them via the Exa API.

3Cited by9 opinions

  1. Graybar Electric Co. v. New Amsterdam Casualty Co.New York Court of Appeals · 1944
  2. Aetna Casualty & Surety Co. v. WoodsTennessee Supreme Court · 1978
  3. National Surety Corp. v. Fischer Steel Corp.Tennessee Supreme Court · 1964
  4. Hogan v. Walsh & Wells, Inc.Tennessee Supreme Court · 1944
  5. Graybar Electric Co. v. New Amsterdam Casualty Co.Tennessee Supreme Court · 1948

4 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API