Legal Opinion

Milwaukee Partners v. Collins Engineers, Inc.

Court of Appeals of Wisconsin

Decided May 5, 1992No. 91-1530PublishedCited by 12 opinions

1Opinion of the CourtFine, J.

This is an action to recover losses Milwaukee Partners claims it sustained as the result of neg ligence by Collins Engineers, Inc. The trial court dismissed Milwaukee Partners' complaint as barred by the six-year statute of limitations for contract actions, holding inapplicable the rule that tolls a statute of limitations until the plaintiff has either discovered or in the exercise of reasonable diligence should have discovered its injury. We reverse.

I

Milwaukee Partners purchased a Milwaukee office building in September of 1983. Prior to buying the building, Milwaukee Partners hired Collins…

2Cases cited17 opinions

  1. Green Spring Farms v. KerstenWisconsin Supreme Court · 1987
  2. Hansen v. AH Robins, Inc.Wisconsin Supreme Court · 1983
  3. A. E. Investment Corp. v. Link Builders, Inc.Wisconsin Supreme Court · 1974
  4. Helmbrecht v. St. Paul InsuranceWisconsin Supreme Court · 1985
  5. Sunnyslope Grading, Inc. v. Miller, Bradford & Risberg, Inc.Wisconsin Supreme Court · 1989

12 more not listed; retrieve them via the Exa API.

3Cited by12 opinions

  1. Insurance Co. of North America v. Cease Electric Inc.Wisconsin Supreme Court · 2004
  2. Hatleberg v. Norwest Bank WisconsinWisconsin Supreme Court · 2005
  3. Stoughton Trailers, Inc. v. Henkel Corp.District Court, W.D. Wisconsin · 1997
  4. Hemberger v. BitzerWisconsin Supreme Court · 1998
  5. Smith Ex Rel. Schoone v. State Farm Fire & Casualty Co.Court of Appeals of Wisconsin · 1995

7 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API