Legal Opinion

United States v. Dexter & Carpenter, Inc.

District Court, S.D. New York

Decided August 28, 1928PublishedCited by 1 opinion

1Opinion of the Court

BONDY, District Judge.

This is a suit to determine the amount of dispatch money earned under a charter party. The charterer deducted from freight money the sum of $4,382.86 for dispatch. The shipowner claims that the proper deduction should have been $1,241.74, and sues to recover the balance of $3,141.12.

Article 4 of the charter party provides: “Lay days for loading, if required by the party of the second part, not to commence before June 21,1920, otherwise lay days to commence from the time steamer is reported ready to load (or within 48 hours after readiness to load if delayed awaiting turn…

2Cases cited4 opinions

  1. The OceanoDistrict Court, S.D. New York · 1906
  2. Israel v. Moore & McCormack Co.District Court, S.D. New York · 1920
  3. Red "R" S. S. Co. v. North American Transport Co.Court of Appeals for the Second Circuit · 1898
  4. West India S. S. Co. v. Field Line, Ltd.District Court, S.D. New York · 1910

3Cited by1 opinion

  1. United States v. Bowring & Co.Court of Appeals for the Second Circuit · 1933