Legal Opinion

H. Piken & Co., Inc. v. Planet Constr. Corp.

Massachusetts Appeals Court

Decided April 30, 1975PublishedCited by 19 opinions

1Opinion of the CourtGoodman, J.

The defendants, the general contractor for the construction of the Brockton High School (Planet) and the surety on its bond, appeal from interlocutory decrees denying the defendants’ motion to recommit and confirming the master’s report and from a final decree awarding to the plaintiff, Planet’s painting subcontractor (Piken), $40,271.35, with interest, for various claims in its bill in equity against the defendants.

1. Among Piken’s claims was an item in the amount of $7,573.30, the cost of wage increases paid by Piken to its employees (as provided by union contracts) for work it was required…

2Cases cited11 opinions

  1. Minot v. MinotMassachusetts Supreme Judicial Court · 1946
  2. O'BRIEN v. DwightMassachusetts Supreme Judicial Court · 1973
  3. Peters v. WallachMassachusetts Supreme Judicial Court · 1975
  4. Tzitzon Realty Co. Inc. v. MustonenMassachusetts Supreme Judicial Court · 1967
  5. Israel v. SommerMassachusetts Supreme Judicial Court · 1935

6 more not listed; retrieve them via the Exa API.

3Cited by19 opinions

  1. Glynn v. City of GloucesterMassachusetts Appeals Court · 1980
  2. Bills v. NunnoMassachusetts Appeals Court · 1976
  3. Bushkin Associates, Inc. And Merle J. Bushkin v. Raytheon CompanyCourt of Appeals for the First Circuit · 1987
  4. Miller v. WinshallMassachusetts Appeals Court · 1980
  5. Dynamics Research Corp. v. Analytic Sciences Corp.Massachusetts Appeals Court · 1980

14 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.