1Opinion of the Court
JONES, District Judge.
The plaintiff’s complaint sets up two causes of action. The first is for breach of contract in failing to deliver certain storm doors and windows within the time provided by the contract. The plaintiff alleges that, solely because of the delays in delivery, it sustained damages due to increased cost of overhead and mechanical supervision ($1,000), increased cost of storage ($320), loss of profits from billings ($18,-900), loss of profits from sales ($20,000), increased cost of material which was substituted for defendant’s products ($3,000), and products made specially…
2Cases cited7 opinions
- Securities & Exchange Commission v. Timetrust, Inc.District Court, N.D. California · 1939
- Best Foods, Inc. v. General Mills, Inc.District Court, D. Delaware · 1943
- Mulloney v. Federal Reserve BankDistrict Court, D. Massachusetts · 1938
- Kellogg Co. v. National Biscuit Co.District Court, D. New Jersey · 1941
- Kuhn v. Pacific Mut. Life Ins.District Court, S.D. New York · 1940
2 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Columbia Broadcasting System, Inc. v. Amana Refrigeration, Inc.Court of Appeals for the Seventh Circuit · 1961
- Boykins v. General Motors Corp.District Court, W.D. Missouri · 1949