Irwin v. United States
United States Court of Claims
1Opinion of the CourtWhaley, Chief Justice
By a contract with the Veterans’ Administration the plaintiffs undertook the construction of a hospital building at Bath, New York. It was an undertaking involving a consideration of $741,800.
The major claim is for excess costs, arising through an allegedly unwarranted prolongation of the time of performance.
Performance was in fact delayed because of difficulties encountered in driving satisfactory piling for the foundations. Actual driving of the piles uncovered subsurface conditions not hitherto known. The specifications described the type of pile to be used, and the routine of driving the…
2Cited by3 opinions
- Joseph H. Roberts v. The United States, Great American Insurance Company, Third-PartyCourt of Appeals for the Third Circuit · 1966
- Pew Forest Products v. United StatesUnited States Court of Federal Claims · 2012
- John Arborio, Inc. v. United StatesUnited States Court of Claims · 1948