Wisconsin Supreme Court
1Opinion of the CourtVinje, C. J.
The defendant assigns as errors (1) that the court erred in finding that the school district board did not consent to the assignment of funds thereafter to become due the contractor, and (2) that the court erred in finding that the school district was not indebted to the bank in the sum of $5,000 out of moneys thereafter becoming due under the architect’s certificates to the contractor. ■
The defendant’s right to recover turns upon the question whether it obtained an assignment from the Otrich-Shrop-*420shire Company that it could enforce against the plaintiff. Assuming, but not deciding, that a…
2Cases cited2 opinions
- Skobis v. FergeWisconsin Supreme Court · 1899
- Cook v. City of MenashaWisconsin Supreme Court · 1899
3Cited by4 opinions
- Allhusen v. Caristo Construction Corp.New York Court of Appeals · 1952
- Sacks v. Neptune Meter Co.Appellate Terms of the Supreme Court of New York · 1932
- Union State Bank v. Peoples State BankWisconsin Supreme Court · 1927
- Sillman v. Twentieth Century-Fox Film Corp.New York Court of Appeals · 1957