Alamo Construction Co. v. United States

United States Court of Claims

Decided November 7, 1949No. 46889Published

1Opinion of the CourtHowell, Judge

Plaintiff sues to recover the sum of $4,227.70, the amount of alleged extra costs incurred in the performance of a re-roofing contract with the defendant.at Camp Hulen, Texas.

*665The invitation for bids provided as follows:

V. Investigation of conditions. — Prospective bidders or their authorized agents are expected to examine the plans and specifications pertaining to the work; to visit the site of the work, to acquaint themselves with all available information, including local conditions and the availability of labor and to make their own estimates of the facilities required and difficulties…

2Cases cited12 opinions

  1. Plumley v. United StatesSupreme Court of the United States · 1913
  2. W. E. Callahan Construction Co. v. United StatesUnited States Court of Claims · 1940
  3. Monroe v. United StatesSupreme Court of the United States · 1902
  4. United States v. John McShain, Inc.Supreme Court of the United States · 1939
  5. Pope v. United StatesUnited States Court of Claims · 1932

7 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API