1. Where an original, $1.2 million construction management/general contractor (CM/GC) construction contract was not approved by the State Controller or his designee, is the State Controller precluded by section 24-30-202(3), C.R.S. (1997), from later approving a contract amendment authorizing additional payments of approximately $17.9 million, where construction work requiring the adjustment in contract value has been completed, and disbursement in excess of the original contract value has already been made?

No. The State Controller retains the authority to…

2Cases cited5 opinions

  1. Mulnix v. Mutual Benefit Life InsuranceSupreme Court of Colorado · 1896
  2. City and County of Denver v. MoormanSupreme Court of Colorado · 1934
  3. Field v. SmallSupreme Court of Colorado · 1892
  4. University of Arizona v. County of PimaCourt of Appeals of Arizona · 1986
  5. Adams County Community Center for Retarded & Seriously Handicapped, Inc. v. StateSupreme Court of Colorado · 1979