1Opinion of the CourtJustice Stone

This cause comes here on a certificate of importance and appeal granted by the Appellate Court for the First District to review a judgment of that court affirming a judgment of the superior court of Cook county against appellant for $60,866.58, and costs, on appellee’s claim for special. damages arising out of delay in completing its contract with defendant.

In April, 1928, appellee (herein referred to as plaintiff) entered into a contract with appellant (herein called defendant) by which plaintiff agreed to construct what is known in the record as “South Crawford Avenue Bridge Approaches…

2Cases cited9 opinions

  1. United States v. BehanSupreme Court of the United States · 1884
  2. Guerini Stone Co. v. P. J. Carlin Construction Co.Supreme Court of the United States · 1919
  3. Ripley v. United StatesSupreme Court of the United States · 1912
  4. Palm & Robertson v. Ohio & Mississippi RailroadIllinois Supreme Court · 1856
  5. Tobey v. PriceIllinois Supreme Court · 1874

4 more not listed; retrieve them via the Exa API.

3Cited by42 opinions

  1. Evra Corp. v. Swiss Bank Corp.Court of Appeals for the Seventh Circuit · 1982
  2. J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc.Illinois Supreme Court · 1994
  3. Chicago College of Osteopathic Medicine v. George A. Fuller Co.Court of Appeals for the Seventh Circuit · 1983
  4. Brewer v. Custom Builders Corp.Appellate Court of Illinois · 1976
  5. Grant Construction Co. v. BurnsIdaho Supreme Court · 1968

37 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API