Hall v. North Plains Concrete Service, Inc.
Supreme Court of Oklahoma
1Per curiam
Insofar as we deem the facts in this cause pertinent to this decision, there is no dispute between the parties. The parties will be referred to as they appeared in the trial court —North Plains Concrete Service, Inc., plaintiff, and Orville Hall and Margaret B. Hall, defendants.
North Plains Concrete Service, Inc., brought this action as original contractor to recover a judgment against the defendants, Orville Hall and Margaret B. Hall, and Jim Lewis, for the purchase price of concrete furnished for the re-erection of a barn by the defendant Lewis on some property owned by the defendants Hall,…
2Cases cited5 opinions
- Gentry-Bowers Lumber Co. v. HamillSupreme Court of Oklahoma · 1919
- Detwiler v. DuncanSupreme Court of Oklahoma · 1947
- Rogers v. Crane Co.Supreme Court of Oklahoma · 1937
- Holmes v. Dolese Bros. Co.Supreme Court of Oklahoma · 1926
- Miles Et Ux. v. ThomasSupreme Court of Oklahoma · 1944
3Cited by3 opinions
- Welling v. American Roofing & Sheet Metal Co.Supreme Court of Oklahoma · 1980
- Diamond Sevens, L.L.C. v. Intelligent Home Automation, Inc.Court of Civil Appeals of Oklahoma · 2010
- Wagnon v. GainesCourt of Civil Appeals of Oklahoma · 1974