Legal Opinion

City of Hot Springs v. Gunderson's, Inc.

South Dakota Supreme Court

Decided July 14, 1982No. 13481PublishedCited by 17 opinions

1Opinion of the Court

MORGAN, Justice.

This appeal arises from defendant, Gun-derson’s Inc. (Gunderson’s), motion to compel arbitration in a suit brought by the City of Hot Springs (City) against Gunderson’s and Phelps-Benz & Associates (Phelps-Benz) for negligence and breach of contract in the construction and design of a city golf course. Only Gunderson’s contract with City contained an arbitration clause. The trial court denied Gunderson’s motion because Phelps-Benz could not be compelled to arbitrate, thus, a great likelihood of multiple suits existed if Gunderson’s prevailed on its motion. We reverse and…

2Cases cited9 opinions

  1. Layne-Minnesota Co. v. Regents of the University of MinnesotaSupreme Court of Minnesota · 1963
  2. School District No. 46 v. Del BiancoAppellate Court of Illinois · 1966
  3. Frederick Contractors, Inc. v. Bel Pre Medical Center, Inc.Court of Appeals of Maryland · 1975
  4. Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.Court of Special Appeals of Maryland · 1974
  5. Warren Brothers Company, Etc. v. Cardi CorporationCourt of Appeals for the First Circuit · 1973

4 more not listed; retrieve them via the Exa API.

3Cited by17 opinions

  1. Thunderstik Lodge, Inc. v. ReuerSouth Dakota Supreme Court · 1998
  2. Anne Arundel County v. Fraternal Order of Anne Arundel Detention Officers & PersonnelCourt of Appeals of Maryland · 1988
  3. Azcon Construction Co. v. Golden Hills Resort, Inc.South Dakota Supreme Court · 1993
  4. Merrill Iron & Steel, Inc. v. Minn-Dak Seeds, Ltd.North Dakota Supreme Court · 1983
  5. Rossi Fine Jewelers, Inc. v. GundersonSouth Dakota Supreme Court · 2002