Kelly v. Ferguson
Appellate Division of the Supreme Court of the State of New York
1Per curiam
The contract provides for payments to the contractor “ not to exceed eighty-five per cent (85%) of the full value of the work done and materials furnished, as the work progresses,” and “ On the last day of each and every calendar month, the Contractors’ statement as herein provided shall be submitted to the Architect, *592covering 85% of the value, proportionate to the amount of the contract, of labor and materials incorporated in the work up to the said last day of the month.” The contractor began work on the 16th day of December, 1922, and on January 1, 1923, applied to the architect for…
2Cases cited4 opinions
- Matter of FreelNew York Court of Appeals · 1896
- Matter of Fuhrmann v. . GravesNew York Court of Appeals · 1923
- People ex rel. Rodgers v. ColerAppellate Division of the Supreme Court of the State of New York · 1900
- Fleischmann v. GravesNew York Supreme Court · 1922
3Cited by1 opinion
- W. A. Brockhurst Co., Inc. v. City of YonkersNew York Supreme Court · 1933