United States ex rel. General Electric Co. v. Southern Construction Co.
District Court, W.D. Louisiana
1Opinion of the Court
BEN C. DAWKINS, JR., Chief Judge.
This action is brought for the use and benefit of plaintiff, General Electric Company (GE), who furnished supplies for construction of the Barksdale Air Force Base Defense Area’s Nike-Hercules Facilities at Bellevue, Louisiana.
GE executed a contract with a subcontractor, Mojave Electric Company, Inc. (Mojave), but had no contractual relationship with the general contractor. Nevertheless, the Miller Act, 40 U.S.C. § 270a et seq., conferred upon the subcontractor’s materialmen a cause of action on the payment bond required to be given by the general contractor…
2Cases cited9 opinions
- Erie Railroad v. TompkinsSupreme Court of the United States · 1938
- United States v. MontgomeryCourt of Appeals for the Third Circuit · 1958
- Socony-Vacuum Oil Company, Incorporated v. Continental Casualty CompanyCourt of Appeals for the Second Circuit · 1955
- Salem Brick & Lumber Co. v. LeSassierSupreme Court of Louisiana · 1901
- McGrath v. American Surety Co.New York Court of Appeals · 1954
4 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- General Electric Company v. Southern Construction Company, Inc.Court of Appeals for the Fifth Circuit · 1967
- Jiménez y Salellas, Inc. v. Maryland Casualty Co.Supreme Court of Puerto Rico · 1965
- United States of America Ex Rel. Dover Elevator Company, Etc. v. General Insurance Company of America, a Washington CorporationCourt of Appeals for the Sixth Circuit · 1964
- United States v. United States Fidelity & Guaranty Co.District Court, N.D. Oklahoma · 1965
- United States v. Southern Construction Co.District Court, W.D. Louisiana · 1964
3 more not listed; retrieve them via the Exa API.