Cochrane Roofing & Metal Co. v. Callahan
Supreme Court of Alabama
1Opinion of the Court
This is an appeal from a judgment entered in a declaratory judgment action.
The single issue presented is whether a contractual undertaking to indemnify another requires that notice of a claim and notice of suit be given to the indemnifying party within a reasonable time where the contract is silent in this regard, and, if so, whether it was given in this case.
The material facts as found by the trial court follow:
Cochrane Roofing and Metal Co., Inc. (subcontractor), sought a declaratory judgment against Steven M. Priola, d/b/a Mark Construction Co., Inc. (contractor), H.S. Callahan (owner),…
2Cases cited9 opinions
- E. M. Loew's Enterprises, Inc. v. SurabianSupreme Court of Connecticut · 1959
- Industrial Tile, Inc. v. StewartSupreme Court of Alabama · 1980
- Avco Manufacturing Corp. v. ConnellySupreme Court of Connecticut · 1958
- United Aircraft Corp. v. O'ConnorSupreme Court of Connecticut · 1954
- Colonial Discount Co. v. Avon Motors, Inc.Supreme Court of Connecticut · 1950
4 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Salter v. HamiterSupreme Court of Alabama · 2004
- Wisconsin Natural Gas Co. v. Gabe's Construction Co.Court of Appeals of Wisconsin · 1998
- Stone Bldg. Co. v. Star Elec. Contractors, Inc.Supreme Court of Alabama · 2000
- BURKES MECH. v. Ft. James-Pennington, Inc.Supreme Court of Alabama · 2004
- West Bend Co. v. Chiaphua Industries, Inc.District Court, E.D. Wisconsin · 2000
8 more not listed; retrieve them via the Exa API.