Western Colorado Power Co. v. Public Utilities Commission
Supreme Court of Colorado
1Opinion of the CourtJustice Moore
We will refer to the parties as follows: to The Western Colorado Power Company as Western; the Public Service Company of Colorado as Public Service; the *265Public Utilities Commission as the Commission; and the Colorado-Ute Electric Association, Inc. as Colorado-Ute.
On May 11, 1962, Colorado-Ute filed an application with the Commission for a “Certificate of Convenience and Necessity.” The object of the application was to permit Colorado-Ute to construct near Hayden, Colorado, a steam electric generating plant with a nominal rating of 150,000 kilowatts, together with associated transmission lines…
2Cases cited32 opinions
- Southern Pacific Terminal Co. v. Interstate Commerce CommissionSupreme Court of the United States · 1911
- Nebbia v. New YorkSupreme Court of the United States · 1934
- Munn v. IllinoisSupreme Court of the United States · 1877
- Terminal Taxicab Co. v. KutzSupreme Court of the United States · 1916
- Idaho Power & Light Co. v. BlomquistIdaho Supreme Court · 1914
27 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- People ex rel. Dunbar v. Gym of America, Inc.Supreme Court of Colorado · 1972
- Public Service Co. v. Trigen-Nations Energy Co.Supreme Court of Colorado · 1999
- Public Service Co. of Colorado v. Public Utilities CommissionSupreme Court of Colorado · 1988
- City of Boulder v. Colorado Public Utilities CommissionSupreme Court of Colorado · 2000
- Salt River Project Agricultural Improvement And Power District v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1968