Meco Systems, Inc. v. Dancing Bear Entertainment, Inc.
Missouri Court of Appeals
1Opinion of the Court
SHRUM, Judge.
This case involves a construction contract whereby MECO Systems, Inc. (Contractor) agreed to build a theater for Dancing Bear Entertainment, Inc. (Owner). The trial court entered summary judgment denying Owner’s claim against Contractor for liquidated damages. Owner claimed entitlement to liquidated damages as Contractor failed to complete the work within the time set by their contract. In a separate summary judgment, the trial court denied Owner’s cross-claim against Marshall-Waters-Woody, Inc. (Architect). The cross-claim alleged that Architect breached its contractual duties…
2Cases cited14 opinions
- ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.Supreme Court of Missouri · 1993
- Cure v. City of JeffersonSupreme Court of Missouri · 1964
- Southwest Engineering Co. v. Reorganized School District R-9Missouri Court of Appeals · 1968
- State Ex Rel. Conway v. VillaMissouri Court of Appeals · 1993
- Myers v. Union Electric Light & Power Co.Supreme Court of Missouri · 1933
9 more not listed; retrieve them via the Exa API.
3Cited by14 opinions
- Robert Baum v. Helget Gas Products, Inc.Court of Appeals for the Eighth Circuit · 2006
- Missouri Consolidated Health Care Plan v. Bluecross Blueshield of MissouriMissouri Court of Appeals · 1999
- Board of Educ. City of St. Louis v. StateMissouri Court of Appeals · 2004
- Family Snacks of North Carolina, Inc. v. Prepared Products Company, Inc., Thomas W. LehmerCourt of Appeals for the Eighth Circuit · 2002
- Cosky v. Vandalia Bus Lines, Inc.Missouri Court of Appeals · 1998